Project   Saurashtra  Pipeline Project (SPP–1)
Location   Pariej & Kanewal, Saurashtra, Gujarat
Type of Project   Raw Water Intake
Concession Authority/Client
  Gujarat Water Supply & Sewerage Board
Contract Value
  INR 1066.8 Mn; USD 27 Mn
 
The project has an unique distinction of laying over 2000 mm MS pipes at 1 Km/day. The main objective of the project was to transfer the excess water from the southern region of Gujarat to the drought prone areas of Saurashtra.

Turnkey execution of water intake and pumping stations with cross country pipeline. Developed the project with subsequent Operation & Maintenance for 24 months
  • Open Intakes at Pariej and Kanewal Tanks
  • Raw water pumping stations at Pariej & Kanewal
  • MS Cross Country Pipeline - 52 KM long
  • Surge Tower at Bamangam with overflow arrangement
  • Sub-station and associated works, supply, erection & commissioning of Pumping Machinery and electrical works and all associated civil & structural works